October 2020 Updates to the Climate Case Charts

ClimateChange-ClimateLaw

Montana Supreme Court Affirmed that Public Service Commission Improperly Rewrote Terms of Solar Project PPA, Including by Eliminating Carbon Adder. The Montana Supreme Court agreed with the district court that the solar project developer was entitled to an agreed-upon rate for energy, a carbon adder, and a 25-year contract term.